2. Prepare the site

Choose locations that satisfy the controller and equipment manufacturers’ environmental, clearance, power, and enclosure requirements. Plan cable routes so that power and data cabling remain appropriately separated and protected.

Before installation, confirm:

  • The GridVolt site record exists and has the correct address and timezone.
  • The site’s connection type matches the approved design.
  • Devices can be assigned using their stable identifiers, not temporary labels.
  • The installer and commissioning engineer have the access they need.

The physical installation points and cable routes are ready, and the GridVolt site record can receive the devices that will be installed.

Compare the prepared site record with the approved survey. Resolve differences before mounting or configuring equipment.